Skip to main content

onenccc

Chimney Lining Projects

Client:

Thermax Ltd.

Consultant:

MPL

Plant:
2x525 MW FGD Project at MPL,Maithon
Job Title:
Borosilicate Lining
Inclusion:
Speciality:
16

2 Nos. 120 Mtr high Chimney Borosilicate Lining Work

Industry:
Power
Year of Execution:
2022
Job Value in Lacs:
(INR)215.35

Client:

Gannon Dunkerley & Co.Ltd., Mumbai

Consultant:

Tata Chemical

Plant:
New Cogen Plant at Tata Chemical, Mithapur
Job Title:
Brick Lining
Inclusion:
Speciality:
15

Supply & application of Insulation & Fireclay Brick Lining Work for 100 Mtr Chimney

Industry:
Chemical
Year of Execution:
2022
Job Value in Lacs:
(INR)150.88

Client:

Larsen & Toubro Ltd., Chennai

Consultant:

Ramco

Plant:
Ramco Cement Ltd., Kolimigundia, Kalvatala
Job Title:
Brick Lining
Inclusion:
Speciality:
14

Supply & application of Brick Lining Work for 90 Mtr height Chimney

Industry:
Cement
Year of Execution:
2021
Job Value in Lacs:
(INR)117.33

Client:

Bharat Heavy Electricals Ltd.

Consultant:

NTPC

Plant:
3x660 MW Barh Super Thermal Power Project, Stage-2 & 3 at NTPC, Barh
Job Title:
Borosilicate Lining
Inclusion:
Speciality:
13

Installation of Borosilicate Glass Block Lining alongwith all associated work in flue can of Unit-2 & 3

Industry:
Thermal Power
Year of Execution:
2021
Job Value in Lacs:
(INR)1788.00

Client:

Larsen & Toubro Ltd.

Consultant:

LSTPP

Plant:
2 X 800 MW Lara Super Thermal Power Plant at Raigada, CG.
Job Title:
Borosilicate Lining
Inclusion:
Speciality:
12

Application of Borosilicate Glass Block System

Industry:
Thermal Power
Year of Execution:
2020
Job Value in Lacs:
(INR)86.75

Client:

Bharat Heavy Electricals Ltd.

Consultant:

NTPC

Plant:
3x660 MW Barh Super Thermal Power Project, Stage-I at NTPC, Barh
Job Title:
Borosilicate Lining
Inclusion:
Speciality:
11

Application of Borosilicate Glass Block Lining System inside the MS Flue Can of existing chimney of FGD Unit-I

Industry:
Thermal Power
Year of Execution:
2019
Job Value in Lacs:
(INR)396.00

Client:

Saint Gobain India Pvt. Ltd., Sriperumbudur

Consultant:

SGIPL

Plant:
SGIPL, Sriperumbudur
Job Title:
Maintenance & Repaiting
Inclusion:
Speciality:
10

Maintenance & Repair Services

Industry:
Glass
Year of Execution:
2019
Job Value in Lacs:
(INR)250.00

Client:

Bharat Oman Refineries Ltd.

Consultant:

BORL

Plant:
BORL, Bina
Job Title:
Shut down
Inclusion:
Speciality:
9

Repair & Maintenance of Chimney Flue of Boilers of Captive Power Plant at BORL, Bina

Industry:
Refinery
Year of Execution:
2017
Job Value in Lacs:
(INR)232.17

Client:

Simplex Infrastructures Ltd., Kolkata

Consultant:

RRVUNL / BHEL

Plant:
RRVUNL, Suratgarh, Rajasthan
Job Title:
275 M high RCC Twin Flue Chimney Brick Lining Work
Inclusion:
Speciality:
8

275 M high RCC Twin Flue Chimney Brick Lining Work

Industry:
Thermal
Year of Execution:
2015
Job Value in Lacs:
(INR)1167.58

Client:

Bharat Aluminium Company Ltd. Korba, CG

Consultant:

BALCO

Plant:
FTP, Smelter Expansion Project, Korba, C.G
Job Title:
Supply & application of 2 Nos. 80 Mtr High RCC Chimney Lining Work of FTP Package
Inclusion:
Speciality:
7

Supply & application of 2 Nos. 80 Mtr High RCC Chimney Lining Work of FTP Package

Industry:
Aluminium
Year of Execution:
2013
Job Value in Lacs:
(INR)290.31

Client:

Larsen & Toubro Ltd., Kalinganagar

Consultant:

TSL

Plant:
Steel at KPO, Orissa
Job Title:
Supply & application of 130 M Sinter Plant Chimney Lining Work
Inclusion:
Speciality:
6

Supply & application of 130 M Sinter Plant Chimney Lining Work

Industry:
Steel
Year of Execution:
2013
Job Value in Lacs:
(INR)246.56

Client:

Simplex Infrastructures Ltd. Baroda

Consultant:

Adani Power

Plant:
Adani Power, Gujarat
Job Title:
220 M High RCC Chimney Lining work (Repeat Order from 2008 to 2012)
Inclusion:
Speciality:
5

220 M High RCC Chimney Lining work (Repeat Order from 2008 to 2012)

Industry:
Power
Year of Execution:
2008
Job Value in Lacs:
(INR)823.14

Client:

UltraTech Cement Ltd., Mumbai

Consultant:

Ultratech

Plant:
Rajarshee, Tadipatri & Rawan Cement Works
Job Title:
Supply & application of Chimney Lining work for Bag House, RABH & TPP
Inclusion:
Speciality:
4

Supply & application of Chimney Lining work for Bag House, RABH & TPP

Industry:
Cement
Year of Execution:
2007
Job Value in Lacs:
(INR)296.54

Client:

Gannon Dunkerley & Co. Ltd. 23A, Netaji Subhas Road, Kolkata - 700001

Consultant:

NALCO - Angul

Plant:
NALCO, Angul, Orissa
Job Title:
220 M High RCC Chimney Lining work
Inclusion:
Speciality:
3

220 M High RCC Chimney Lining work

Industry:
Aluminium
Year of Execution:
2006
Job Value in Lacs:
(INR)270.15

Client:

CESC Ltd.,

Consultant:

CESC

Plant:
Plant :TGS, Titagarh
Job Title:
Shut down
Inclusion:
Speciality:
2

Acid Proof Lining work for Chimney No.1

Industry:
Electricity
Year of Execution:
2005
Job Value in Lacs:
(INR)46.47

Client:

National Building Construction Corp. Ltd., New Delhi

Consultant:

RSEB / DCL

Plant:
Rajasthan State Electricity Board, Suratgarh
Job Title:
Brick Lining
Inclusion:
Speciality:
1

220 M High Twin Flue RCC Chimney Lining Work

Industry:
Electricity
Year of Execution:
1997
Job Value in Lacs:
(INR)160.00